ATC-YRK · Attenuation

Attenuation tank beside York station

A long attenuation tank beside the railway buildings at York station, lined in 0.75mm geomembrane and built in a long, narrow excavation.

Location
York
Region
North Yorkshire
Sector
Rail
Completed
2026
Aquatech crew laying membrane in the tank excavation beside the railway buildings at York station
Rec · ATC-YRKYork — Rail

Attenuation · York

Rail

Ref
ATC-YRK
Region
North Yorkshire
Sector
Rail
Year
2026
01

What we did

Geotextile and a 0.75mm geomembrane laid the length of the excavation and welded, the crate system built inside, then the wrap closed and the pipe connections sealed through it.

02

The tricky bits

A tight railway site with a brick building on one side and a deep trench on the other. When the delivery came up 15 side panels short, one end was left to close out properly on a return visit.

03

What we delivered

A lined, wrapped tank with its base weld pressure-tested to 1 bar and recorded, on a constrained station site.

04

The membrane

The tank was lined in 0.75mm geomembrane, the thickness we fit on most tanks. Every joint was heat-welded rather than taped.

05

Programme

The first visit was signed off on site in mid-June 2026, with the open end recorded on the sign-off as work still to complete. The shortfall was across the width at one end, so that end was built out and closed on the return visit.

Project datasheetATC-YRK
System
Geocellular crates
Membrane
0.75mm geomembrane, welded
QA
Base weld tested to 1 bar
Sector
Rail
System · Attenuation Tanks

On site · York

Crates built up inside the lined excavation at York station
Rec · ATC-YRKYork — Rail
Operatives working along the wrapped crate run at York station, with welding kit in the foreground
Rec · ATC-YRKYork — Rail
Next in the log · ADP-BOG

AD-plant containment bund lining

Tell us about your project

Quote back within one working day