What we did
We deployed protective fleece and a welded impermeable membrane across the lined area, detailed to the structures on site and tested at the seams.
The tricky bits
Working on a live industrial site around existing plant and structures means careful deployment and clean welds in a working environment.
What we delivered
A tested, documented lining installation delivered to the site's requirements.
The lining
Protective fleece went down first, so the formation can't puncture the membrane. The impermeable membrane was laid over it and heat-welded panel to panel, then detailed around the pipe penetrations and structures on site.
Testing and handover
A test weld was carried out and recorded before cover, and the installation was handed over with its weld test record and QA documentation.
- Application
- Attenuation tank lining
- Membrane
- Welded over fleece
- Sector
- Waste / industrial
On site · Liverpool
On site


3,500m² lined attenuation basin
Tell us about your project
Quote back within one working day