ADP-BOG · Lining & containment

AD-plant containment bund lining

Secondary containment lining for an anaerobic digestion plant — the welded barrier that keeps a leak inside the bund and out of the ground and watercourse.

Location
Bognor Regis
Region
West Sussex
Sector
Energy / AD
Completed
2026
Two Aquatech operatives welding the containment membrane at the Bognor Regis AD plant
Rec · ADP-BOGBognor Regis — Energy / AD

Lining & containment · Bognor Regis

Bund

Ref
ADP-BOG
Region
West Sussex
Sector
Energy / AD
Year
2026
01

What we did

We lined the containment bund with a welded impermeable membrane over protective fleece, dressed up the bund walls and detailed at every penetration and transition. Secondary containment only works if it's genuinely tight, so every seam was extrusion welded.

02

The tricky bits

Containment lining lives on the details — corners, the transition up the bund wall, and each penetration. All were individually formed and sealed so the finished bund holds its rated volume with no weak points.

03

What we delivered

A tested, documented containment system that gives the operator — and the regulator — confidence that a spill stays where it can be dealt with.

04

What the bund does

The lined bund around the AD plant does two jobs. If the plant is ever breached, it holds the contents as secondary containment. Day to day, it keeps surface water out of the plant itself.

05

The liner

The bund was lined in 1.5mm HDPE, with every seam extrusion welded and tested. Much of the work was forming the liner around the plant's many existing penetrations.

There was no formal lining specification for the bund, and the liner was held down with interlocking precast concrete blocks made on site. Neither is how we usually work, so the details were agreed with the site team as the job went.

06

Programme

The work was done over two site visits, five days of installation in all, and handed over on schedule in May 2026. Extra materials needed partway through were sourced at short notice.

Project datasheetADP-BOG
Application
Secondary containment
Membrane
Welded over fleece
Sector
Anaerobic digestion
Detailing
Walls, corners, penetrations
System · Gas & Hydrocarbon Membranes

On site · Bognor Regis

Membrane welded up to the digester tank wall at the Bognor Regis AD plant
Rec · ADP-BOGBognor Regis — Energy / AD
Penetration fitting sealed into the containment membrane at Bognor Regis
Rec · ADP-BOGBognor Regis — Energy / AD
Next in the log · ATC-CHE

Attenuation tank, pressure-tested to record